Tuesday, April 14, 2009

REMODELING CONTRACTORS - CONSTRUCTION COMPANY -Part 6

Dear Readers
The contents of this publication has been prepared by Engineers of long experience in implementing Remodelings-Industrial Construction- Construction of Buildings
We appreciate any comments ,that help improve this blog


GENERAL OUTGOINGS -Part 3

Here we are going to analyze the cost of the salary, for the Construction of a New Work or Reformation where laborers work 10 daily hours from Monday to Saturday
According to the labor legislation the firsts 8 hours of Monday to Friday and 4 hours of Saturday are ordinary hours

HOURS PAID WEEKLY

Monday to Friday 8hs x 5 days................................40 hs
Monday to Friday 50 % 2hs x 5 days...................... 15 hs
Saturday normal hs ... 4hs x 1 day ............................ 4 hs
Saturday to the 100 % ... 6hs x 1 day....................... 12 hs

TOTAL PAID HOURS....................................................71 HS

OPERATED HOURS WEEKLY

Monday to Saturday..10 hs x 6 days...........................................60 hs

If we divide 71/60=1,1833 we should affect the Staff's Cost for 18% more


One should add to the above

The incidence of the Climatic factors in work's place

At cold or very hot zones, the performances of the tasks are inferior to what's Standard
It can be also a normal zone but in season of a lot of precipitations, snowfalls or winds
There are tasks, for example ....the movement of Soils, the filling of concrete or the welding that see themselves very affected by the climatic conditions

The need or no of Negotiating the Work Permits to initiate Tasks

In Refineries or sectors at the risk of fire or explosion, its necessary manufacture Permits Work, before manufacturing them, they measure for example the risk of explosion .....These situations can take minimum one waiting hour for day

If the staff arrive for his means to the work or is relocated by The Company

If the base where are living the Staff are separated from the place of work, the Company should take care of the transfer and should pay the travel time

The execution of Elevation Work’s has other cost; according to the local Agreements and besides there is a decrease of performances, in order to work in State of risk

The percentage of sick persons or accident victims

Generally we Estimated in a 8 %

If the staff works on the reform of an Existent Plant, an important decrease in the Standard performance near the 30 % should be foreseen in this case..For example at a Refinery (including permits work)

We concluded, that we have to be very CAREFUL when we make a ESTIMATION and that need staff with field EXPERIENCE for these task